✓ Completed

Before the Build

Land acquisition, permits, site prep, and everything that had to happen before breaking ground.

Actual cost: $79,370
November 2022
Land Purchase
Purchased 3 acres on a ridge in Swain County, NC — Fontana Lake HOA area near Bryson City.
✓ Complete
March 2023
Property Survey
Survey completed establishing property boundaries.
✓ Complete
May 2023
Septic Permit Issued
Swain County health department issued the septic permit.
✓ Complete
January 2024
Septic Trenching Begins
Initial trenching for septic system installation begins.
✓ Complete
June 2024
Site Prep — Land Clearing
Excavator on site, clearing three acres of ridge line and establishing the building pad.
✓ Complete
November 2024
Tree Removal
Additional tree clearing to fully open the build site.
✓ Complete
June 2025
Septic System Complete
All trenching and septic installation finalized.
✓ Complete
February 2026
Architect Engaged
Architectural plans underway for the 2,052 sq ft cabin.
✓ Complete
May 2026
Building Permit
Swain County building permit issued.
✓ Complete
Phase 1

Basement + Floor System

Footers, block walls, under-slab plumbing, concrete slab, waterproofing, sill plates, basement wall framing, floor trusses, and subfloor. Target: December 2026.

Budget: $81,726 · Spent so far: $67,983
Jun 25, 2026
Footers Dug + Poured
Footer trenches dug June 17, concrete poured June 25. The build begins.
✓ Complete
Jul 6, 2026
Block Walls Complete
Basement block walls laid up.
✓ Complete
Jul 20, 2026
Under-Slab Plumbing Complete
Plumber finished the under-slab rough-in.
✓ Complete
Jul 30, 2026
Basement Slab Poured
Concrete basement slab poured.
✓ Complete
Aug 20, 2026
Foundation Complete
Basement waterproofing finished. Foundation complete.
✓ Complete
Oct 2, 2026
Sill Plates Installed
Pressure-treated sill plates anchored to the block walls.
✓ Complete
Scheduled Oct 26, 2026
Basement Wall Framing
Basement walls get framed in two sessions: Oct 26-30 and Nov 11-14. Has to be done before the floor trusses go on.
Upcoming
TBD
Floor Trusses + Subfloor
Floor trusses set and subfloor down, after the basement framing. Planned for December. Closes out Phase 1.
Upcoming
Phase 2

Upper Structure Dried-In

First and second floor framing, roof trusses, sheathing, and standing seam metal roof on. Target: May 2027.

Budget: $41,006
TBD
Framing Begins
Upcoming
TBD
Roof Dried In
Upcoming
Phase 3

Envelope Close-Up + Rough-Ins

Windows, doors, siding, exterior trim — then rough electrical, plumbing, HVAC, and insulation. Target: September 2027.

Budget: $73,634
TBD
Rough-In Complete
Upcoming
Phase 4

Interior Finishes + Certificate of Occupancy

Drywall, paint, flooring, cabinets, fixtures, trim, appliances — then final inspections and the CO. Target: December 2027.

Budget: $66,220
TBD
Interior Work
Upcoming
TBD
Certificate of Occupancy
Upcoming

Total Project: $341,956

$147,353 spent so far, from the land purchase through the build work done to date. Certificate of Occupancy target: December 2027.