✓ Completed

Before the Build

Land acquisition, permits, site prep, and everything that had to happen before breaking ground.

November 2022
Land Purchase
Purchased 3 acres on a ridge in Swain County, NC — Fontana Lake HOA area near Bryson City.
✓ Complete
March 2023
Property Survey
Survey completed establishing property boundaries.
✓ Complete
May 2023
Septic Permit Issued
Swain County health department issued the septic permit.
✓ Complete
January 2024
Septic Trenching Begins
Initial trenching for septic system installation begins.
✓ Complete
June 2024
Site Prep — Land Clearing
Excavator on site, clearing three acres of ridge line and establishing the building pad.
✓ Complete
November 2024
Tree Removal
Additional tree clearing to fully open the build site.
✓ Complete
June 2025
Septic System Complete
All trenching and septic installation finalized.
✓ Complete
February 2026
Architect Engaged
Architectural plans underway for the 2,052 sq ft cabin.
✓ Complete
May 2026
Building Permit
Swain County building permit issued.
✓ Complete
Phase 1

Basement + Floor System

Footers, block walls, under-slab plumbing, concrete slab, floor trusses, and subfloor. Target: October 2026.

Est. Cost: $77,821
June 2026
Foundation Starts
Footer forms set, concrete poured — the build begins.
Upcoming
TBD
Foundation Complete
Upcoming
Phase 2

Upper Structure Dried-In

First and second floor framing, roof trusses, sheathing, and standing seam metal roof on. Target: May 2027.

Est. Cost: $32,756
TBD
Framing Begins
Upcoming
TBD
Roof Dried In
Upcoming
Phase 3

Envelope Close-Up + Rough-Ins

Windows, doors, siding, exterior trim — then rough electrical, plumbing, HVAC, and spray foam insulation. Target: September 2027.

Est. Cost: $73,634
TBD
Rough-In Complete
Upcoming
Phase 4

Interior Finishes + Certificate of Occupancy

Drywall, paint, flooring, cabinets, fixtures, trim, appliances — then final inspections and the CO. Target: December 2027.

Est. Cost: $66,220
TBD
Interior Work
Upcoming
TBD
Certificate of Occupancy
Upcoming

Total Project: $327,767

Land + pre-construction ($77,336 already invested) + four phases of construction ($250,431). Certificate of Occupancy target: December 2027.